Jubilee School

Client: Hillcrest

Date: Spring 2014

Convert old office building to school- reconfiguring existing ground floor offices into classrooms and administrative offices with school hall and vocational teaching areas, also to provide 6 classrooms on the first floor with library and independent learning areas.

The original start date of the contract (Jan 2014) was delayed by the client, works commenced at the beginning of March 2014 with Practical Completion by middle of May 2014, working to ensure that the building met with all Local Authority and Ofsted requirements.